Skip to main content
Corvus
GPR

GPR scanning before drilling — why it matters

Why pre-drill GPR scanning is the cheapest insurance on a UK construction site, and what happens when it is skipped.

Pre-drill GPR scanning is the most common reason concrete scanning is commissioned on UK construction sites — and it is also the easiest cost to argue down when budget is tight. That is a mistake. The economics of pre-drill scanning are clear: the cost of a half-day scan is a small fraction of the cost of a single struck cable, severed conduit, or damaged post-tension tendon. Here is why pre-drill scanning matters, and what happens when it is skipped.

What can be inside a slab

A typical reinforced concrete slab in a modern UK commercial building can contain:

  • Top and bottom layers of reinforcement bar.
  • Embedded electrical conduit (often plastic).
  • Embedded data and comms ducts.
  • Embedded heating, plumbing, or sprinkler pipework.
  • Cast-in fixings and ferrules.
  • Post-tension tendons (in PT floors).
  • Voids, honeycombing, and other defects.
  • Mesh, fibre reinforcement, or other ancillary steel.

Drawings, even where they exist, rarely capture all of this. Plant layouts get changed during construction. Late additions get cast in. As-builts lag the construction by months. The “drawings on file” almost never match the as-built one-to-one.

What goes wrong when you don’t scan

The list of things that have gone wrong when contractors have drilled without scanning is long and well-documented:

  • Severed electrical cables. A live cable strike is a safety incident, an electrical outage, and a remedial repair all at once. The cost runs into thousands of pounds even on minor incidents and into tens of thousands on major ones.
  • Severed water and gas services. Floods are immediate and expensive. Gas strikes are dangerous.
  • Damaged conduit and comms infrastructure. Repairing a severed comms or data conduit may require chasing out and re-pouring slab segments.
  • Damaged post-tension tendons. This is the worst-case scenario. PT tendons are highly stressed and any damage can lead to expensive repair work, structural reassessment, and sometimes large-scale remediation.
  • Damaged sprinkler pipework. A breach often means flood damage to occupied space below.
  • Project delays. Even where the strike is not catastrophic, the time lost to making the area safe, isolating services, repairing damage, and re-investigating before resuming work usually dwarfs the time the scan would have taken.

The economics

A pre-drill scan on a typical area is a half-day job. The marginal cost to a project is small compared with:

  • The day-rate of the trades doing the drilling.
  • The cost of any temporary works around the drilling.
  • The cost of an unplanned strike.
  • The reputational cost on a high-profile project.

For most projects, the breakeven point on pre-drill scanning is somewhere around “one strike avoided every 50 jobs”. The actual strike rate without scanning is much higher than that. Pre-drill scanning is one of the cheapest pieces of insurance available on a construction site.

When it is non-negotiable

Some situations admit no compromise:

  • Post-tension floors. A struck PT tendon is the most expensive avoidable mistake on any modern building. Pre-drill scanning is the standard mitigation.
  • Live electrical environments. Healthcare, data centres, manufacturing — anywhere a live strike has cascading consequences.
  • Heritage and listed buildings. Drilling without scanning into historic fabric risks irreversible damage.
  • Engineered slabs. Transfer slabs, post-tension floors, beam-and-block slabs all have specific reinforcement layouts that cannot be guessed at.
  • Drilling close to slab edges or services. Where any service is known to run nearby, pre-drill scanning is the only defensible practice.

What good practice looks like

Pre-drill GPR is part of the contractor’s RAMS for any project involving penetration of structural concrete. The standard approach is:

  1. Mark the proposed drilling positions on the slab.
  2. Brief the surveyor on the slab type, history, and known plant.
  3. Survey the marked positions and a reasonable buffer around them.
  4. Mark detectable reflectors found.
  5. Reposition any drilling target that conflicts with a reflector.
  6. Sign off the drilling plan against the survey.

A short pre-drill loop adds modestly to the day rate of the drilling team but produces a defensible, low-risk programme. Insurers and main contractors increasingly require this loop for any non-trivial drilling on RC structures.

When it is skipped

The temptation to skip the scan usually comes from one of three places: tight programme, tight budget, or “it’s just a few small holes”. The first two are addressable in the planning. The third is a category error: a small hole through a PT tendon causes the same damage as a large one, and a small hole through a live cable trips the same incident as a large one.

If your project has reinforced concrete and you have any doubt at all about what is inside it, the right answer is almost always to scan first.

Ready to see what's beneath the surface?

Tell us what you're working on. We'll come back within a working day with a quote, a method, and a date in the diary.